What were the main challenges?

The main challenge was that the waste was on the first floor. We had to protect the staircase and take all the waste down 2 flights.

The other challenge was that the building was occupied. This meant that there were restrictions on when we could take the waste out and perform noisy operations.

Strip out included:

As part of the strip out we had to remove the following:

  • Ceiling grid
  • Ceiling tiles
  • Partitions (plasterboard / glass / wood)
  • Carpet tiles
  • Reception desk/area and tiled flooring
  • Office furniture

Waste removed included:

The kinds of waste materials that we had to take away were:

  • Cables
  • Tiles
  • Rubble
  • Plasterboard
  • Timber
  • Carpet tiles
  • Plastic
  • Metals